Community Partners for Affordable Housing became
the asset manager for Metzger Park Apartments
in the Fall of 1996. Day to day operations
of the 32 unit complex are managed by Income Property
Management.
Since taking over the property, CPAH has made
a number of improvements:
|
|
1. This project was built decades ago. Since that
time, extensive development in Tigard, Beaverton
and Portland have exacerbated storm drainage problems
along Ash Creek. CPAH was able to work with Clean
Water Services and Washington County's Office
of Community Development to complete a stream
bank stabilization project in this area. While
no one can prevent floods, this project minimizes
the likelihood of such, and stabilizes the buildings
for the long run.
2. A small computer room/library was set up.
|
|
3. In December 2000, CPAH began a major rehabilitation
project at Metzger Park to replace the siding
on both apartment blocks, and to repair decks
and roofs. As part of CPAH's effort to follow
green building practices wherever possible, Hardiplank
siding was chosen for this project. To date, all
siding has been replaced and deck repairs and
painting have been completed.
|
4. In 2003, the children's play structure was replaced. |
5, In August 2005, both parking lots were resurfaced. |
|
|
 |
|
|
 |
|